Tuesday, May 4, 2010

4-way Inspection

We scheduled our first 4- way inspection (Building, Electrical, Mechanical, Plumbing) on April 22, 2010.

The inspector left a list of 20 items to fix before we could pass. We spent the next week working on all of the items.We scheduled our second 4-way (Building, Electrical, Mechanical, Plumbing) on April 30, 2010. We passed everything except one item, something to do with washers and bolts for our laundry room wall. We passed enough to go a head and start the Insulation and Exterior work.


We have an Inspection for our Stone papering and insulation – Thurs May 6, 2010 @ 9:00

May 4, 2010

We had our Exterior guys come and put our soffit and fascia up along with papering and netting for our stone. We will be able to get the stone started as soon as we pass the inspection.







































We had our Insulation company come May 4, 2010 and they put insulation in the walls, when we pass the inspection we can go ahead with sheetrock and insulation in the attic.














Kitchen














Family room














Front Room




















Hallway




















Master bathroom














Basement


























Garage

We will be picking up siding on Wed May 5, 2010 and start siding the outside of our house.


We have Sheet Rock Scheduled to go in/up on Monday May 10, 2010

We have been busy picking out colors of stone/rock, siding, tile, cabinets, countertops.

We have had to figure out were to put lights, light switches, plugs, T.V., Telephone jacks and lots of stuff like that.